September 2014 Planning Update

Fundraising

EMU Suter Science Campaign gift plan

  • Thanks to the generous support of 460 alumni, donors, and foundations, EMU exceeded its goal of $7 million for lab renovations a full year earlier than planned! Total gifts and commitments as of December 31, 2013 equal $7,581,811!
  • With $7 million now in place to address the east wing/lab renovations, we turn our attention to several additional urgent needs in the west wing, including the iconic S-106 lecture hall, classrooms, and HVAC and sprinkler systems. Of the additional estimated $3.3 million needed to fund the complete transformation of the entire Suter Science Center, over $770,000 is already in place.

Review the Suter Science Campaign gift plan

Estimated renovation timeline

  • March – May 2014: Asbestos abatement in the east wing/lab areas and S-104 “the head room.”
  • April 2014: Demolition of S-104 begins; construction completed by September 1, 2014.
  • June 2014: East and south labs renovations begin.
  • December 2014: South and east classrooms construction complete.
  • January 2015: North labs renovations begin for completion by August 2015.

History of the renovation design and planning process

EMU established a design concept committee responsible for creating a design concept that maximizes the educational value of the Suter Science Center within the confines of the available budget.

Learn more about the committee, preliminary budget, and architectural priorities for the upcoming renovation…